The project involved the removal of 68,000 sq. ft. of the existing roof
system, installation of a new fluid applied roof membrane in an IRMA
configuration, related sheet metal flashings, and installation of a new
window washing davit system.
Installation
of pedestrian protection and signage to protect, direct and control
flow of employees and visitors to and from the facility. Installation
of davit support required off-hour drilling of concrete to install
thru-bolts inside offices throughout the facility.
|